Background
The purpose of the Change Job Price Matrix Tool is to update a job's price matrix to another price matrix with options to preserve existing discounts (alter pricings) and existing pricings (alter discounts).
Before you begin
- Ensure you are logged into the Elda(Chrome) Scheduler Application. See our article Getting Started with Scheduler for more.
Steps to follow:
- In the Scheduler main window, click the Job# header then type the Job number (Searching for a Job)
-
On the left side of the main window, navigate to Tools > Admin.
-
In the new window, go to Change Job Price Matrix tab.
-
Click the dropdown menu then select a different price matrix than the job's price matrix.
-
Click on Alter Discount/Preserve Pricing radio button.
If the job has Rebar Price Matrix enabled in Job Details (Job > Job Details > Pricing/Discounts tab) and you select Alter Discount/Preserve Pricing option, you will see "Current rebar price matrix pricing will be preserved" message. -
Click Refresh Grid. This should show all the pricing and discounts for the selected price matrix.
-
Make further adjustments in the Discount column if necessary. Once done, click the Apply Pricing to Job button.