1. In Estimator, open the estimate you wish to authorise a variation for.
2. Select an estimate section to authorise
3. Then select the Est. Variation button.
4. This will open the Estimate Variation window.
5. Within the ‘Estimate’s section with Variations’ field will be a list of the variations associated with the selected estimate.
6. Select the variation you wish to Authorise
7. Then select the ‘Authorise’ button
8. You will then be notified of the new final total of the estimate - This will include any authorised variations.
9. Select ‘Okay’
10. You will be prompted to enter your pin number to authorise the variation.
11. Once authorised, the variation will be locked and displayed as “Authorised”, and you are no longer able to make any changes or delete the variation.